On 31 March East West Rail launched its 10 week consultation regarding the east west rail project connecting Oxford and Cambridge (via Bedford to Bletchley Marston Vale line).

 

https://eastwestrail.co.uk/consultation   The consultation closes on 9 June 2021.

 

The consultation includes proposals to:

 

1. Close the Woburn Sands and Aspley Guise level crossings, with new road bridges.

2. Or retain the Woburn Sands level crossing, with up to 40 minute delays.

 

Attached are two of the key diagrams and the high level points impacting us locally are detailed below.

 

Woburn Sands See attached)

 

East West Rail propose two options for the station:

 

Option 1: Extend the existing platforms to the west in order to accommodate longer trains. 

Option 2: Relocate the station to the west. 

 

There are two proposals for the level crossing:

 

Option 1 proposes closing the level crossing and building a new road from Hardwick Road to Bow Brickhill Road, bypassing The Leys and then on to Newport Road in Wavendon. A bridge would be provided at School Crossing in Woburn Sands. To view the suggested plan click here 

 

Option 2 proposes retaining the current level crossing, however the barriers would be down for up to 40 minutes per hour. A new foot footbridge would be provided west at Woodley’s Farm and School Crossing in Woburn Sands would remain closed. To view the suggested plan click here

 

 

How to respond to this consultation

 

You can share your views using the online feedback form available here (https://communityhub.eastwestrail.co.uk/consultation-feedback/survey_tools/feedback) or by emailing your comments to EWR at  consultation@eastwestrail.co.uk  or writing to us via FREEPOST East West Rail. 

 

Alternatively, you can request a paper copy of the feedback form to be sent to you by emailing EWR at contact@eastwestrail.co.uk  or by calling us on 0330 134 0067.

 

The closing date for the consultation is 9 June 2021.